The bridge was delivered the morning of June 4, 2021. JP&K Construction blocked off one lane of traffic during installation to safely offload the prefabricated steel truss from the truck and swing it into place onto the prepared cast-in-place concrete abutments. The bridge was set in a single piece, making the installation quick and minimizing disruption on this busy jobsite.
Jennifer Mayfield, Project Manager for Studio E Architects, was on site for the bridge installation and declared that “It fit like a glove, I was so impressed! Great work Jeff + Team!”
To check out a video of this installation from an aerial view, click here: https://youtu.be/2HNGRMwSThg (Credit to Jeff Peterson, JP&K Construction Management Inc.)
To check out a video of this installation from the ground, click here: https://youtu.be/90dw1AutQHo (Credit to Jennifer Mayfield, Studio E Architects)